PROJECT SUMMARY – Project is the construction of pedestrian and drainage enhancements to the US Highway 65 intersection at West Main St. This will include removals, unclassified excavation, erosion control, asphalt roadway patching, curb and gutter, pedestrian sidewalk, drainage improvements, traffic control, and minor signing and striping.

PROJECT LOCATION – The intersection of SH65 and Main St. in downtown Cedaredge. The west side of the intersection both north and south sides.

APPROXIMATE SCHEDULE – The project is expected to last 12 weeks. It will start February 26, 2018 and complete on or about 5/15/18.

WHAT TO EXPECT – A full road closure of Main St. in both directions from SH65 to S 2nd St. One crosswalk will always be open to allow access to the east side of SH65. Please keep a lookout for sidewalk closures.

CONTACT INFORMATIONsh65mainst@westerngravel.com or call (888)526-3531